We have been working with the Royal Canadian Armed Forces bases for over 25 years including Trenton, Kingston, and Petawawa. We have conducted projects of infrastructure, institutional, and commercial in a time frame of 2022 – 2024.
Client Name: Kingston Base for Royal Canadian Armed Forces
Location: Kingston, Ontario
Project Name: Kingston HR24 Lift Station
Budget: $1,000,000 – $5,000,000
Strong Enterprises worked on this project as a joint venture acting as the General Contractor. Some of the general scope of work consisted of site demolitions, concrete forming and concrete reinforcing, new electrical, and extensive exterior improvements.
Requirements of Project:
- Demolition of the existing HR24 sewage lift Station
- Construction of a new HR24 Sewage Lift Station at new location
- Construction of a 250mm PVC gravity sewer from existing maintenance hold
Client Name: Defence Construction Canada
Location: Trenton RCAF Base
Project Name: RCAF Rd Entrance Project-Reconfigure Alert Boulevard
Budget: $3,000,000
Reconfiguration and reconstruction of the Alert Boulevard pavement structure and Westwin Avenue intersection inclusive of vehicle inspection lay-bys, parking lot reconfiguration with some full depth pavement, roadway and parking area lighting. This work also includes High Security retractable anti-ram vehicle barricades, traffic control spikes/tire shredders, security fence, security bollards, guard house and associated power communications and lighting requirements.
Requirements of Project:
- Site Demolitions and removals
- Concrete works (forming, reinforcing, cast in place)
- Traffic control and specialized signage
- Special Construction (prefabricated buildings)
- Electrical
- Communications
- Earthworks; aggregate materials, site grading, excavation etc.
- Exterior improvements; asphalt paving, concret walks, curbs and gutters
- Chain link fencing
- Utilities
- Transportation; anti-ram vehicle barrier system, traffic restraint system
Client Name: Defence Construction Canada
Location: 8 Wing CFB Trenton
Project Name: B117 Retrofit Sewage Lift Station
Budget: $153.481,76
This project involved the comprehensive enhancement and new construction work on Building 117’s Sewage Lift Station. The scope included upgrading safety features with a new fall protection system, constructing a protective enclosure for the existing stairwell, and adding a storage enclosure on the pre-existing concrete pad. Additionally, a new walkway was constructed to improve accessibility, and explosion-proof lighting and receptacles were installed in the storage area to enhance safety and operational efficiency. These modifications were designed to meet modern standards and ensure the long-term reliability of the facility.
Requirements of project:
- Demolition for minor works
- Hazardous building materials general requirements
- Concrete
- Metal fabrications
- Opening – Metal doors and frames
- Finishes
- Electrical
- Earthwork